R. No. Key Performance Indicators Information Remarks
1 Total Sanctioned seats (GCVT + NCVT ) (Senior + Junior Batch including both)  1008 junior
2 Total Number of Admission Forms Sold till 31st August 2016..... 3500
3 Total Number of Admission Forms Returned till 31st August 2016... 3500
4 Total Number of Trainees who took Admission in Junior Batch as on 31st August 2016........ 880
5 Total Number of Trainees in Senior Batch as on 30th Jun 2016........ NONE
6 Total Number of On-Roll Trainees (Junior + Senior Batches) as on End of Reporting Month. NONE
7 Percentage utilization of student seating capacity NONE
8 Retention Rate (On roll * 100/ Admission) NONE
9 No. of trades.(GCVT + NCVT) NONE
10 No. of batches (GCVT + NCVT) NONE
11 Total Number of Trainees who appeared in the Final Examination in July 2016... NONE
12 Total Number of Trainees who passed in the Final Examination in July 2016... NONE
13 Pass out percentage in August 2016... NONE
14 No. of sanctioned post of teaching staff (All Trade,Maths, Drawing, Social Studies, English and others) NONE
15 No. of currently filled posts of teaching staff (All Trades,Maths,Drawing,Social Studies,English and others) NONE
16 No. of sanctioned posts for teaching staff (on Contract Basis - Recruitment by ITI Principal) NONE
17 No. of currently filled posts of teaching staff (on Contract Basis - Recruitment by ITI Principal) NONE
18 No. of sanctioned post of non-teaching staff (including Principal) NONE
19 No. of currently filled posts of non-teaching staff (including Principal) NONE
20 No. of teaching staff sent for Training (from 01 April 2008 onwards till date) NONE
21 No. of Trainings attended by ITI Principal (from 01 April 2008 onwards till date)
22 Total Plan Budget Provision for the current financial year 2016-17 NONE
23 Total Plan Budget Expenditure during the current financial year 2016-17 NONE
24 Total Non-Plan Budget Provision for the current financial year 2016-17 NONE
25 Total Non-Plan Budget Expenditure during the current financial year 2016-17 NONE
26 Total Budget Provision (Plan + Non-Plan) for Students' Stipend in ITI during current financial year 2016-17 NONE
27 Total Expenditure on Students' Stipend in ITI during the current financial year 2016-17 (upto 31 Aug 2017) NONE
28 Percentage Expenditure against Provision on Stipend during current financial year 2016-17(upto 31 Aug 2016) NONE
29 Total Budget Provision (Plan + Non-Plan) for Raw Materials in ITI during current financial year 2016-17 NONE
30 Total Expenditure on Raw Materials in ITI during the current financial year 2016-17 (upto 31 Aug 2017) NONE
31 Percentage Expenditure against Provision on Raw Materials during current financial year 2016-17 (upto 31 Aug 2017) NONE
32 Revenue Generation (if any during the current financial year) NONE
33 Staff Utilization (Students-instructor ratio) Full time student to all staff (including non-teaching staff) NONE
Full time student to teaching staff NONE
34 Short term courses conducted till date 31/08/2013 during the year 2016-17 (MES and others) No.of Batches NONE
No.of persons trained NONE
No. of trainees who have completed Motor Driving School Training. NONE
35 No. of trainees who successfully completed and passed the CCC Course. During 2015-16 A. ITI Staff -
B. Other Government Employees -
36 Progress of Placement Advisory Bureau (fill up separate review form where applicable, otherwise state Not Applicable) NONE
37 Progress of Language Lab (fill up separate review form where applicable, otherwise state Not Applicable) NONE
38 No of Campus Interview held during the Year 2014-2015
39 No. of Students who got jobs Year 2014-2015 (do not include figures of Apprenticeship Training )
No. of Expert Faculties invited from Industries as Guest Lecturer (Attach a Separate Paper with List of Names, designation, telephone, mobile, Name of industry, complete address)
40 No.of Industrial Visits by trainees during the Year 2015-2016.
41 No.of Workshops and Seminars held (from 01 April. 2009 onwards)
42 No.of IMC Meeting held Current Year Financial year 2016-17
Progressive (Starting from formation of IMC)
43 No.of students from Polytechnics and Engg. Colleges who came and delivered guest lecture (from 01 April 2014 onwards till date)

Address

Refinery Road Gorwa Vadodara

Last Update on : 11/03/2020

Quick Contact

Tel : 0265-2280413
Mob : 0265-2280413
Email : prlgorwaiti@gmail.com

Visitor Counter

      
Html Valid   Html Valid
Copyright © GOVT ITI GORWA . All rights reserved. | Designed & Developed By : pCube Software Solution.